Work Profile Report [39W260]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 4305(1)/।।।(2)/11-16(मु0मं0घो0)/2011 दिनांक 16.09.2011
TS Amount (lakhs) : 23.23 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
50.40
Resanction Cost :
50.40
Tentative Cost :
50.40
Exp. Upto Last Fy :
16.27
For CFY 2025-2026
Remaining :
34.13
Demand :
4.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
16.27
Work completed
Sanction on : 13 years 7 months ago
16 Sep 2011
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 6 years 3 weeks ago
31 Mar 2019
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
fद्वतीय चरण की स्वीकृfत के अन्तर्गत कार्य पूर्ण। -- as on 15-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: