Work Profile Report [39W223]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 6985/।।।(2)/10-18(प्रा0आ0)/2010 टी0सी0-4 दिनांक 03.02.2011
TS Amount (lakhs) : 14.47 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
37.80
Resanction Cost :
37.80
Tentative Cost :
37.80
Exp. Upto Last Fy :
21.75
For CFY 2025-2026
Remaining :
16.05
Demand :
4.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
21.75
Work completed
Sanction on : 14 years 2 months ago
03 Feb 2011
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on : 2 years 3 weeks ago
31 Mar 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण के अन्तर्गत कार्य पूर्ण। कुछ कास्तकारों का मुआवजा वितरण शेष है। -- as on 15-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: