Work Profile Report [39W1140]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. सं0 1/266914/2025 ई-फाइल संख्या 50408 /लोक निर्माण अनुभाग-2 दिनांक 08.01.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
243.44
Resanction Cost :
243.44
Tentative Cost :
243.44
Exp. Upto Last Fy :
0.09
For CFY 2025-2026
Remaining :
243.35
Demand :
150.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.09
Construction Started
Sanction on : 3 months 2 weeks ago
08 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on : 11 months 6 days from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सोलिंग कोट हेतु पत्थर एकत्रीकरण कार्य प्रगति में। -- as on 15-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: