Work Profile Report [39W1140]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. सं0 1/266914/2025 ई-फाइल संख्या 50408 /लोक निर्माण अनुभाग-2 दिनांक 08.01.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
243.44
Resanction Cost :
243.44
Tentative Cost :
243.44
Exp. Upto Last Fy :
0.09
For CFY 2025-2026
Remaining :
243.35
Demand :
150.00
Allotment :
46.93
Exp in CFY :
46.93
Total Up to Date Exp :
47.02
Construction Started
Sanction on : 5 months 1 day ago
08 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
40 %
Tentative Completion date on : 9 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.00 किमी0 में सोलिंग कोट & Inter Coat का कार्य पूर्ण। Top कोट का कार्य प्रगति पर। -- as on 02-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand