Work Profile Report [39W1129]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. ।/239943/2024 ई-फाईल सं0 54684 /लोक निर्माण अनुभाग-2 दिनांक 13.09.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
97.52
Resanction Cost :
97.52
Tentative Cost :
97.52
Exp. Upto Last Fy :
76.38
For CFY 2025-2026
Remaining :
21.14
Demand :
20.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
76.38
Work completed
Sanction on : 7 months 1 week ago
13 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 11 months 6 days from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
1.10 किमी0 में पीसी द्वारा सतह लेपन का कार्य पूर्ण। दायित्व शेष। -- as on 15-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: