Work Profile Report [38W730]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E-file No. 52001 Dt. 04/12/2024
TS Amount (lakhs) : 71.34 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
71.34
Resanction Cost :
71.34
Tentative Cost :
71.34
Exp. Upto Last Fy :
20.35
For CFY 2025-2026
Remaining :
50.99
Demand :
45.00
Allotment :
40.00
Exp in CFY :
0.00
Total Up to Date Exp :
20.35
Construction Started
Sanction on : 6 months 5 days ago
04 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
50 %
Tentative Completion date on : 2 weeks 6 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
चैड़ीकरण एवं दीवार निर्माण, नाली निर्माण, सोलिंग एवं इंटर कोट का कार्य पूर्ण। टाॅप कोट का कार्य प्रगति में। -- as on 02-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: