Administrative Approval Detail : शासनादेश संख्या:- 5082/।।।(2) /2023-01 (प्रा0आ0)/ 2023 दिनांक 09.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
327.59
Resanction Cost :
327.59
Tentative Cost :
327.59
Exp. Upto Last Fy :
321.52
For CFY 2025-2026
Remaining :
6.07
Demand :
4.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
321.52
Work completed
Sanction on : 1 year 5 months ago
09 Nov 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 5 months 3 weeks ago
30 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 21-Dec-2024
Assets :