Work Profile Report [37W304]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 789/।।।(2)/18-05 (एम0एल0ए0) /2017 टी0सी0 दिनांक 23/02/2018
TS Amount (lakhs) : 147.82 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
147.82
Resanction Cost :
158.91
Tentative Cost :
158.91
Exp. Upto Last Fy :
152.00
For CFY 2025-2026
Remaining :
6.91
Demand :
1.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
152.00
Work completed
Sanction on : 7 years 2 months ago
23 Feb 2018
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 6 months 3 weeks ago
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 11-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: Pinder river (Paithani)