Work Profile Report [37W176]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 333/।।। (2)/14 -46 (प्रा0आ0)/2013 दिनांक 21/1/2014
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
48.60
Resanction Cost :
48.60
Tentative Cost :
48.60
Exp. Upto Last Fy :
19.16
For CFY 2025-2026
Remaining :
29.44
Demand :
8.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
19.16
Work completed
Sanction on : 11 years 3 months ago
21 Jan 2014
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मुआवजा वितरण कार्य प्रगति में। -- as on 10-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: