Work Profile Report [32W274]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : मुख्य अभियन्ता, स्तर-। का पत्र सं. 6064(1)/।। (2)/11-37 (प्रा.आ.)/2011, दिनांक 15.11.2011
TS Amount (lakhs) : 89.04 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
89.04
Resanction Cost :
89.04
Tentative Cost :
0.00
Saving
89.04
Exp. Upto Last Fy :
71.81
For CFY 2025-2026
Remaining :
17.23
Demand :
4.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
71.81
Construction Started
Sanction on : 13 years 5 months ago
15 Nov 2011
Physical Progress:
At start of FY 2025-2026 :
95 %
Up to Date :
95 %
Tentative Completion date on : 11 months 6 days from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
प्रतिकर वितरण किया जा रहा है। द्वितीय चरण का कार्य पूर्ण। -- as on 01-Jul-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: