Work Profile Report [32W1324]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासन का ई-फाइल संख्या 84450/02, दिनांक 20.03.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
124.06
Resanction Cost :
133.06
Tentative Cost :
133.06
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
133.06
Demand :
100.76
Allotment :
62.85
Exp in CFY :
35.80
Total Up to Date Exp :
35.80
Construction Started
Sanction on : 8 months 3 weeks ago
20 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
25 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 9 has been counted as tentative cost increased from 124.06 to 133.06 . -- as on 16-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: