Work Profile Report [30W1560]

ग्राम गवांणा के क्यारकी नामेतोक मे 15 मी0 स्पान की पैदल पुलिया का निर्माण कार्य
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 27/VIII-DP/लो0नि0वि0 (01)/जि0यो0/2024-25 Dt. 11/12/2024

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

18.00

Resanction Cost :

18.00

Tentative Cost :

18.00

Exp. Upto Last Fy :

0.11

For CFY 2025-2026

Remaining :

17.89

Demand :

17.99

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.11

Construction Started

Sanction on : 4 months 1 week ago

11 Dec 2024

Physical Progress:

At start of FY 2025-2026 :

40 %

Up to Date :

40 %

Tentative Completion date on : 2 months 5 days from now

30 Jun 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Bridge
1 (15m)
1 (15m)
0 (0.000m)
1 (15m)
1 (15.000m)
0 (0.000m)

Remark

view all

कार्य प्रगति पर है। -- as on 04-Apr-2025

Rating : 86

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: