Administrative Approval Detail : E File No. 37632/02 Lo.Ni.Vi. Anubhag-2
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
139.17
Resanction Cost :
139.17
Tentative Cost :
139.17
Exp. Upto Last Fy :
40.80
For CFY 2025-2026
Remaining :
98.37
Demand :
50.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
40.80
Construction Started
Sanction on : 7 months 4 days ago
20 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
45 %
Up to Date :
45 %
Tentative Completion date on : 7 months 5 days from now
30 Nov 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
G3 का कार्य प्रगति पर है। -- as on 07-Apr-2025
Assets :
Work not linked with IM