Work Profile Report [30W1535]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : E File No. 56385
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
428.78
Resanction Cost :
428.78
Tentative Cost :
428.78
Exp. Upto Last Fy :
341.60
For CFY 2025-2026
Remaining :
87.18
Demand :
87.18
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
341.60
Work completed
Sanction on : 1 year 1 month ago
15 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 3 weeks ago
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 11-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand