Work Profile Report [30W1531]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E File No. 69779
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.77
Resanction Cost :
53.77
Tentative Cost :
53.77
Exp. Upto Last Fy :
28.92
For CFY 2025-2026
Remaining :
24.85
Demand :
15.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
28.92
Construction Started
Sanction on : 1 year 1 month ago
14 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
25 %
Up to Date :
25 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर । -- as on 14-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: