Work Profile Report [30W1521]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : 212/III(2)/2024-01(Pra.Aa)/2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
148.22
Resanction Cost :
204.74
Tentative Cost :
204.74
Exp. Upto Last Fy :
187.13
For CFY 2025-2026
Remaining :
17.61
Demand :
17.61
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
187.13
Work completed
Sanction on : 1 year 2 months ago
31 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 7 months 3 weeks ago
30 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 11-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: