Work Profile Report [30W1378]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 2011/2-34 पौड़ी
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
76.25
Resanction Cost :
76.25
Tentative Cost :
76.25
Exp. Upto Last Fy :
44.29
For CFY 2025-2026
Remaining :
31.96
Demand :
31.96
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
44.29
Work completed
Sanction on : 3 years 3 weeks ago
31 Mar 2022
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 11-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: