Work Profile Report [30W1154]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0- 1291(4)/।।।(2)/19-02 (एम0एल0ए0)/17 टी0सी0 दि0 08-03-19
TS Amount (lakhs) : 322.85 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
322.85
Resanction Cost :
322.85
Tentative Cost :
322.85
Exp. Upto Last Fy :
310.05
For CFY 2025-2026
Remaining :
12.80
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
310.05
Work completed
Sanction on : 6 years 1 month ago
08 Mar 2019
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 5 months ago
31 Oct 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान एवं पार्ट-।। का कार्य पूर्ण। -- as on 01-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: