Work Profile Report [2W677]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E file No. 48456 date 07.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : अनुरक्षण ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
111.52
Resanction Cost :
111.52
Tentative Cost :
111.52
Exp. Upto Last Fy :
33.13
For CFY 2025-2026
Remaining :
78.39
Demand :
70.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
33.13
Construction Started
Sanction on : 1 year 1 month ago
07 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
75 %
Tentative Completion date on : 1 month 3 weeks from now
20 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
क्रॉस ड्रेनेज व दीवारों का कार्य पूर्ण। 1.00 कि0मी0 में पी सी का कार्य प्रगति पर। -- as on 08-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: