Administrative Approval Detail : शा0सं0 ।/285828/2025 (ई0 फाईल सं0 68062) दि0 25.03.2025
TS Amount (lakhs) : 27.9 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
27.90
Resanction Cost :
27.90
Tentative Cost :
27.90
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
27.80
Demand :
25.00
Allotment :
0.10
Exp in CFY :
0.10
Total Up to Date Exp :
0.20
Construction Started
Sanction on : 2 months 2 weeks ago
25 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
5 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
लेविल डेªसिंग का कार्य प्रगति में -- as on 22-May-2025