Work Profile Report [25W1200]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 ।/234870/2024 (ई0 फाईल सं0 54118) दि0 23.08.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
170.03
Resanction Cost :
170.03
Tentative Cost :
170.03
Exp. Upto Last Fy :
46.81
For CFY 2025-2026
Remaining :
123.22
Demand :
100.00
Allotment :
28.32
Exp in CFY :
28.32
Total Up to Date Exp :
75.13
Construction Started
Sanction on : 9 months 2 weeks ago
23 Aug 2024
Physical Progress:
At start of FY 2025-2026 :
55 %
Up to Date :
75 %
Tentative Completion date on : 5 months 2 weeks from now
25 Nov 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 का कार्य प्रगति में। -- as on 22-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: