Work Profile Report [25W1181]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 । /196330 /2024 (ई0 फाईल सं0 68062) दि0 06.03.2024
TS Amount (lakhs) : 66.39 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
66.39
Resanction Cost :
66.39
Tentative Cost :
66.39
Exp. Upto Last Fy :
46.67
For CFY 2025-2026
Remaining :
19.72
Demand :
19.70
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
46.67
Work completed
Sanction on : 1 year 1 month ago
06 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 16 hours ago
03 Apr 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष। -- as on 30-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand