Work Profile Report [24W1016]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुुभाग - 2 ई फाईल सं0 77368 दि0 20.09.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
51.92
Resanction Cost :
51.92
Tentative Cost :
51.92
Exp. Upto Last Fy :
26.97
For CFY 2025-2026
Remaining :
24.95
Demand :
24.95
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
26.97
Work completed
Sanction on : 7 months 4 days ago
20 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 3 days from now
28 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 07-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand