Work Profile Report [24W1011]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुुभाग - 2 ई फाईल सं0 53601 दि0 13.09.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
40.00
Resanction Cost :
40.00
Tentative Cost :
40.00
Exp. Upto Last Fy :
32.45
For CFY 2025-2026
Remaining :
7.55
Demand :
7.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
32.45
Construction Started
Sanction on : 7 months 1 week ago
13 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
50 %
Tentative Completion date on : 5 months 2 weeks from now
15 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
200 मी0 लम्बाई में 1 मार्ग में कार्य पूर्ण। दूसरे मार्ग पर मिट्टी का कार्य प्रगति पर। -- as on 01-Jan-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand