Work Profile Report [23W1248]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/249197/2024, e-file no.- 50220
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
98.50
Resanction Cost :
98.50
Tentative Cost :
98.50
Exp. Upto Last Fy :
9.96
For CFY 2025-2026
Remaining :
88.54
Demand :
55.01
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
9.96
Construction Started
Sanction on : 6 months 1 day ago
23 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 31-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand