Work Profile Report [23W1225]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : G.O. no.- I/139122/2023 e-file no.- 51571
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
161.98
Resanction Cost :
161.98
Tentative Cost :
161.98
Exp. Upto Last Fy :
145.36
For CFY 2025-2026
Remaining :
16.62
Demand :
4.06
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
145.36
Work completed
Sanction on : 1 year 9 months ago
20 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 month 1 week ago
15 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 05-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand