Work Profile Report [23W1212]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/176048/2023 e-file no.- 62543
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.53
Resanction Cost :
47.53
Tentative Cost :
36.00
Saving
11.53
Exp. Upto Last Fy :
43.61
For CFY 2025-2026
Remaining :
3.92
Demand :
3.92
Allotment :
2.61
Exp in CFY :
2.61
Total Up to Date Exp :
46.23
Work completed
Sanction on : 1 year 5 months ago
18 Dec 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 6 months 4 weeks ago
12 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 08-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand