Work Profile Report [22W1573]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E file no. 51385/59, dt. 27.01.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
205.62
Resanction Cost :
205.62
Tentative Cost :
205.62
Exp. Upto Last Fy :
11.68
For CFY 2025-2026
Remaining :
193.94
Demand :
58.25
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
11.68
Sanction on : 2 months 4 weeks ago
27 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 205.62 has been counted as tentative cost increased from to 205.62 . -- as on 01-Feb-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: