Work Profile Report [22W1568]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E-file No. 70174/60, dt. 23.12.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
150.30
Resanction Cost :
150.30
Tentative Cost :
150.30
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
150.20
Demand :
120.00
Allotment :
50.93
Exp in CFY :
50.93
Total Up to Date Exp :
51.03
Construction Started
Sanction on : 8 months 2 weeks ago
23 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
48 %
Tentative Completion date on : 1 month 5 days from now
15 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
यू0यू0एस0डी0ए0 द्वारा पाईप लाईन का कार्य से बाधित। -- as on 30-Aug-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: