Work Profile Report [22W1554]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 548/25-32/ZY 2024-25
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
10.00
Resanction Cost :
10.00
Tentative Cost :
10.00
Exp. Upto Last Fy :
9.26
For CFY 2025-2026
Remaining :
0.74
Demand :
0.74
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
9.26
Sanction on : 7 months 4 weeks ago
27 Aug 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 10 has been counted as tentative cost increased from to 10 . -- as on 04-Jan-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand