Work Profile Report [22W1548]

वार्ड नं0-50 में आदर्श नगर में गली नो 1 में सी0सी0 रोड़ का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 548/25-32/ZY 2024-25

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

5.72

Resanction Cost :

5.72

Tentative Cost :

5.72

Exp. Upto Last Fy :

3.00

For CFY 2025-2026

Remaining :

2.72

Demand :

2.72

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

3.00

Sanction on : 7 months 4 weeks ago

27 Aug 2024

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Jobs
1
1
1
-

Remark

view all

Overall Excess requirement 5.72 has been counted as tentative cost increased from to 5.72 . -- as on 04-Jan-2025

Rating : 115

No Forest Case in The Work

Hindrance / Bottleneck :

Assets :

Work not linked with IM

Bridges on The Basis of AI: