Work Profile Report [22W1481]

जिला स्तरीय विकास प्राधिकरण के अंतर्गत आर०टी०ओ० ऑफिस से संधू फार्म , लालपुर नायक मार्ग का निर्माण कार्य
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 2101/NJVP/23-24

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

619.10

Resanction Cost :

619.10

Tentative Cost :

619.10

Exp. Upto Last Fy :

391.01

For CFY 2025-2026

Remaining :

228.09

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

391.01

Construction Started

Sanction on : 1 year 4 months ago

07 Feb 2024

Physical Progress:

At start of FY 2025-2026 :

30 %

Up to Date :

30 %

Tentative Completion date on : 3 months 1 week ago

14 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
3
0.000
3
0.000
0.000

Remark

view all

कार्य प्रगति पर -- as on 20-Mar-2024

Rating : 63

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: