Work Profile Report [22W1191]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : श्शासनादेश संख्या 643/।।। (2)/20-60 (एम0एल0ए0)/2017 टी0सी0, दिनाॅक 12.02.2020 द्वारा स्वीकृत
TS Amount (lakhs) : 189.44 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
189.44
Resanction Cost :
189.69
Tentative Cost :
173.27
Saving
16.42
Exp. Upto Last Fy :
173.27
For CFY 2025-2026
Remaining :
16.42
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
173.27
Work completed
Sanction on : 5 years 10 months ago
12 Feb 2020
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 years 8 months ago
31 Mar 2021
Actual Completion Date : 4 years 3 months ago
08 Sep 2021
Physical Linear Components
Remark
Overall Saving 16.42 has been recorded as expected cost of work reduced from 189.69 to 173.27 . -- as on 12-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: