Work Profile Report [20W556]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुभाग -2 के ई0 फाईल संख्या -51659 दि0 14.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
210.47
Resanction Cost :
210.47
Tentative Cost :
210.47
Exp. Upto Last Fy :
20.39
For CFY 2025-2026
Remaining :
190.08
Demand :
150.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
20.39
Construction Started
Sanction on : 1 year 1 month ago
14 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
20 %
Tentative Completion date on : 6 months 6 days from now
31 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान का कार्य प्रगति में है। -- as on 04-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand