Work Profile Report [1W765]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : E - File No. 75269/2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.20
Resanction Cost :
3.20
Tentative Cost :
3.20
Exp. Upto Last Fy :
1.87
For CFY 2025-2026
Remaining :
1.33
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1.87
Survey work done
Sanction on : 6 months 2 days ago
22 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
40 %
Tentative Completion date on : 11 months 6 days from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 3.2 has been counted as tentative cost increased from to 3.20 . -- as on 10-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: