Work Profile Report [1W712]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E File No. 49618 Dated- 06.08.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
178.36
Resanction Cost :
178.36
Tentative Cost :
178.36
Exp. Upto Last Fy :
25.07
For CFY 2025-2026
Remaining :
153.29
Demand :
100.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
25.07
Construction Started
Sanction on : 8 months 2 weeks ago
06 Aug 2024
Physical Progress:
At start of FY 2025-2026 :
35 %
Up to Date :
35 %
Tentative Completion date on : 1 year 6 months from now
30 Oct 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कल्वर्ट व दीवार कार्य प्रगति पर। -- as on 09-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: