Administrative Approval Detail : E - File No. 56385/III(2)/2024-01(PRA AA)/2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
42.20
Resanction Cost :
982.90
Tentative Cost :
982.90
Exp. Upto Last Fy :
81.50
For CFY 2025-2026
Remaining :
901.40
Demand :
893.88
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
81.50
Construction Started
Sanction on : 1 year 1 month ago
15 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
20 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
4.00 कि0मी0 में सड़क सुरक्षा का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 09-Apr-2025
Assets :