Work Profile Report [1W586]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 - ई फाई संख्या 46885 दिनंाक 03 मार्च, 2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
223.86
Resanction Cost :
223.86
Tentative Cost :
200.00
Saving
23.86
Exp. Upto Last Fy :
155.87
For CFY 2025-2026
Remaining :
67.99
Demand :
24.00
Allotment :
23.86
Exp in CFY :
23.86
Total Up to Date Exp :
179.73
In Maintenance After Completion
Sanction on : 2 years 9 months ago
03 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 2 weeks ago
31 Mar 2025
Actual Completion Date : 11 months 2 weeks ago
31 Dec 2024
Physical Linear Components
Remark
कार्य पूर्ण 12/2024 दायित्व अवशेष -- as on 12-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: