Work Profile Report [1W586]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 - ई फाई संख्या 46885 दिनंाक 03 मार्च, 2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
223.86
Resanction Cost :
223.86
Tentative Cost :
223.86
Exp. Upto Last Fy :
178.47
For CFY 2025-2026
Remaining :
45.39
Demand :
20.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
178.47
Work completed
Sanction on : 2 years 1 month ago
03 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 3 days ago
31 Mar 2025
Actual Completion Date : 3 months 3 weeks ago
31 Dec 2024
Physical Linear Components
Remark
कार्य पूर्ण 12/2024 दायित्व अवशेष -- as on 02-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: