Work Profile Report [19W748]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 256/III(3)/2024-01(C.R.I.F.)2022 Dated : 29-02-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2143.00
Resanction Cost :
2125.30
Tentative Cost :
2125.30
Exp. Upto Last Fy :
1,194.83
For CFY 2025-2026
Remaining :
930.47
Demand :
930.47
Allotment :
273.10
Exp in CFY :
273.10
Total Up to Date Exp :
1,467.94
Construction Started
Sanction on : 1 year 3 months ago
29 Feb 2024
Physical Progress:
At start of FY 2025-2026 :
45 %
Up to Date :
75 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
39 किमी0 लम्बाई में बी0सी0 का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 06-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand