Administrative Approval Detail : 36(2)/23/106-2(8)/2013 Dated : 29-03-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1067.87
Resanction Cost :
1067.87
Tentative Cost :
1067.87
Exp. Upto Last Fy :
887.18
For CFY 2025-2026
Remaining :
180.69
Demand :
180.69
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
887.18
Construction Started
Sanction on : 2 years 2 months ago
29 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
93 %
Tentative Completion date on : 1 month 6 days ago
03 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
समस्त भवनों के स्ट्रक्चर का कार्य पूर्ण। फिनिंसिंग के अन्तर्गत पेन्टिंग का काय। प्रगति पर। -- as on 06-Jun-2025