Work Profile Report [19W533]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1310/।।।(2)/19-55(एम0एल0ए0)/2017 टी0सी0 दिनांक 07-03-2019
TS Amount (lakhs) : 280.42 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
280.42
Resanction Cost :
280.42
Tentative Cost :
280.42
Exp. Upto Last Fy :
259.85
For CFY 2025-2026
Remaining :
20.57
Demand :
3.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
259.85
In Maintenance After Completion
Sanction on : 6 years 1 month ago
07 Mar 2019
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 1 month ago
28 Feb 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण, IN 5 YEAR MAINTENANCE -- as on 12-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: