Work Profile Report [19W131]

जनपद चम्पावत में धूनाघाट से बसौट तक मोटर मार्ग का नव निर्माण। (प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0स0 3851(1)/।।।(2)/11-64(एम0एल0ए0)/ 2011 दिनांक 07-07-2011

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

75.60

Resanction Cost :

75.60

Tentative Cost :

75.60

Exp. Upto Last Fy :

26.89

For CFY 2025-2026

Remaining :

48.71

Demand :

25.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

26.89

Phase1 DPR Submitted

Sanction on : 13 years 9 months ago

07 Jul 2011

Physical Progress:

At start of FY 2025-2026 :

99 %

Up to Date :

99 %

Tentative Completion date on : 3 years 3 weeks ago

31 Mar 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
6
6
6
-

Remark

view all

वर्तमान में उक्त कार्य की सैद्वान्तिक एवं विधिवत दोनों स्वीकृति प्राप्त हो चुकी है, स्वीकृति उपरान्त कार्य की नव निर्माण स्टेट-1 का आंगणन नई दरों पर गठित कर मुख्य अभियन्ता अल्मोडा को प्रेषित। मुख्य अभियन्ता अल्मोडा द्वारा मुआवजा वितरित करने के उपरान्त आंगणन प्रेषित करने हेतु निर्देशित किया गया है जिसके क्रम में मुआवजा वितरित करने की कार्यवाही की जा रही है। -- as on 28-Nov-2024

Rating : 99

Forest Case Pending At : 18: Final Approval

Hindrance / Bottleneck : Sanction Required form Govt

Assets :

Work not linked with IM

Bridges on The Basis of AI: