Work Profile Report [18W896]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई पत्रावली सं0 19329/2022 लोक निर्माण अनुभाग-2 देहरादून दिनांक 6 दिसम्बर 2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
345.69
Resanction Cost :
345.69
Tentative Cost :
345.69
Exp. Upto Last Fy :
22.36
For CFY 2025-2026
Remaining :
323.33
Demand :
267.86
Allotment :
313.45
Exp in CFY :
313.45
Total Up to Date Exp :
335.80
Work completed
Sanction on : 1 year 1 week ago
06 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
100 %
Tentative Completion date on : 3 months 2 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.550 कि.मी. लम्बाई में पी0सी0 का कार्य पूर्ण। -- as on 17-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: