Work Profile Report [18W871]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन की ई पत्रावली सं0 38109 लोक निर्माण अनुभाग-2 देहरादून दिनांक 16 अक्टूबर 2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
105.83
Resanction Cost :
105.83
Tentative Cost :
105.83
Exp. Upto Last Fy :
16.54
For CFY 2025-2026
Remaining :
89.29
Demand :
60.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
16.54
Construction Started
Sanction on : 6 months 1 week ago
16 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
20 %
Tentative Completion date on : 8 months 6 days from now
31 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2 किमी0 सोलिंग का कार्य पूर्ण। अवशेष कार्य प्रगति पर है। -- as on 27-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: