Administrative Approval Detail : E-File No. 37533/2022 Lok Nirman Anubhag-2 date 27-02-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
231.44
Resanction Cost :
231.44
Tentative Cost :
231.44
Exp. Upto Last Fy :
0.09
For CFY 2025-2026
Remaining :
231.35
Demand :
75.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.09
in Tendering Stage
Sanction on : 1 month 4 weeks ago
27 Feb 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
निविदा प्रक्रिया गतिमान। -- as on 09-Apr-2025