Work Profile Report [17W393]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E-File No. 52192
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
283.42
Resanction Cost :
283.42
Tentative Cost :
283.42
Exp. Upto Last Fy :
87.97
For CFY 2025-2026
Remaining :
195.45
Demand :
160.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
87.97
Construction Started
Sanction on : 1 year 3 months ago
26 Dec 2023
Physical Progress:
At start of FY 2025-2026 :
31 %
Up to Date :
31 %
Tentative Completion date on : 4 months 2 weeks from now
12 Sep 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
स्कपरों का निर्माण कार्य एवं दीवारों का निर्माण कार्य पूर्णI WBM G-1 का कार्य प्रगति पर है । -- as on 02-Apr-2025
Assets :
© PWD Uttarakhand