Work Profile Report [17W193]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 2062/(1)/।।।(2)/13-56 (प्रा0आ0)/2012 दिनांक 20-3-2013
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
39.06
Resanction Cost :
39.06
Tentative Cost :
32.00
Saving
7.06
Exp. Upto Last Fy :
28.55
For CFY 2025-2026
Remaining :
10.51
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
28.55
Work completed
Sanction on : 12 years 1 month ago
20 Mar 2013
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date : 3 years 3 weeks ago
31 Mar 2022
Physical Linear Components
Remark
Overall Saving 7.06 has been recorded as expected cost of work reduced from 39.06 to 32 . -- as on 11-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand