Work Profile Report [15W859]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E File No. 53127 Lok Nirman Anubhag-2 dt 30-11-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
759.30
Resanction Cost :
759.30
Tentative Cost :
759.30
Exp. Upto Last Fy :
304.26
For CFY 2025-2026
Remaining :
455.04
Demand :
455.04
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
304.26
Construction Started
Sanction on : 1 year 2 months ago
30 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
45 %
Up to Date :
45 %
Tentative Completion date on : 7 months 2 weeks from now
12 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
240 mtr. work complete and awshesh work in progress. -- as on 07-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: