Work Profile Report [15W771]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : Computer No. I/57981/2022 Dated 24 August 2022
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
87.91
Resanction Cost :
87.91
Tentative Cost :
42.00
Saving
45.91
Exp. Upto Last Fy :
19.84
For CFY 2025-2026
Remaining :
68.07
Demand :
30.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
19.84
Construction Started
Sanction on : 2 years 7 months ago
30 Aug 2022
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on : 5 months 5 days from now
30 Sep 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वर्तमान में पहाड़ कटान का कार्य प्रगति में है, लगभग 80% कार्य किया जा चुका है । -- as on 04-Apr-2025