Work Profile Report [15W767]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : GO. No. 506/III(2)/21-44 (MLA)/2017 T.C.-I Dated 07.01.2022
TS Amount (lakhs) : 157.96 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
157.96
Resanction Cost :
157.96
Tentative Cost :
145.96
Saving
12.00
Exp. Upto Last Fy :
150.08
For CFY 2025-2026
Remaining :
7.88
Demand :
0.77
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
150.08
In Maintenance After Completion
Sanction on : 3 years 3 months ago
07 Jan 2022
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 10 months 1 day ago
23 Jun 2024
Actual Completion Date : 9 months 2 weeks ago
04 Jul 2024
Physical Linear Components
Remark
Overall Saving 12 has been recorded as expected cost of work reduced from 157.96 to 145.96 . -- as on 09-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: