Work Profile Report [15W457]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 428/।।।(2)/16-14(मु0मा0घो0)/2015 दिनांक 23.01.2016
TS Amount (lakhs) : 1.63 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
155.20
Resanction Cost :
155.20
Tentative Cost :
155.20
Exp. Upto Last Fy :
83.98
For CFY 2025-2026
Remaining :
71.22
Demand :
40.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
83.98
Construction Started
Sanction on : 9 years 3 months ago
23 Jan 2016
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
60 %
Tentative Completion date on : 8 months 6 days from now
31 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग पर मुआवजा प्रस्ताव गठित कर एवं राजस्व विभाग से सत्यापन उपरान्त मुआवजा वितरण किया जा रहा है । -- as on 04-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: